Hope School Alterations & New Classrooms, Santa Barbara

Viola, Inc. · Santa Barbara

Finished library with rows of wood shelving and a round reading table under freshly painted walls and soffits — Hope School alterations and new classrooms, Santa Barbara

New classrooms and campus alterations at Hope School, 3970 La Colina Rd, Santa Barbara, for Viola, Inc. Purple Painting’s scope includes full interior and exterior painting of the new building, partial painting of most existing buildings, and replacement and painting of fixed and suspended ceilings. The project has multiple phases over approximately 3 years.

Type
Public Works
Location
3970 La Colina Rd, 93110
Client
Viola, Inc.
Completed
2025

Construction of new classrooms at Hope School in Santa Barbara, including full painting interior and exterior of new building. Alterations to the rest of the school campus, including partial painting of most existing buildings. Replacement and painting of multiple fixed and suspended ceilings and touch-up painting at all associated renovation areas. This project has multiple phases and is set to run for approximately 3 years.

How we did it

  1. Prime and paint the new classroom walls and ceilings

    New gypsum board walls, including walls up to 18 feet high, and the vaulted ceilings were given a full prime coat and two coats of finish.

  2. Spot prime and paint existing walls

    In the existing buildings, existing drywall and CMU walls were spot primed over patches and given two coats of finish.

  3. Varnish the exposed beams

    The glu-lam beams in the new classrooms were changed from paint to clear coat: sanded to open the grain, treated with wood conditioner, sealed with sanding sealer, sanded smooth and finished in two coats of semi-gloss interior varnish.

  4. Paint doors, frames and ductwork

    New and existing wood and metal doors and frames, exposed ductwork and the fire pipe were painted.

  5. Paint the exterior of the new classrooms

    Cement plaster walls and soffits, fiber cement fascia boards, downspouts, and the steel trellis rafters, beams and columns were painted.

  6. Paint the alteration exteriors

    The guardrails and handrails, gutter, redwood fascia, reglets and flashing, mechanical enclosure CMU wall and redwood gate were painted in the existing buildings.

  7. Paint the ceiling tiles